If you have any enquiries, please email This e-mail address is being protected from spam bots, you need JavaScript enabled to view it Reynell Building Facade works to be completed by the end of May 2011 Internal fit out works to be completed in June 2011 Roof terrace works to be completed in July 2011
Tower Block Tower crane will be dismantled and removed mid May 2011. Major traffic movements will occur during this period Facade works to be completed in June 2011 Hoarding removal to be completed in June 2011 Internal fit out works to be completed in July 2011 Minor traffic movements and noise from construction equipment is ongoing
Cumberland Street Carpark Street works on Cumberland Street to be completed in July 2011 Minor traffic movement and construction noise is ongoing
|