Reynell Building

Facade works to be completed by the end of May 2011

Internal fit out works to be completed in June 2011

Roof terrace works to be completed in July 2011

 

Tower Block

Tower crane will be dismantled and removed mid May 2011. Major traffic movements will occur during this period

Facade works to be completed in June 2011

Hoarding removal to be completed in June 2011

Internal fit out works to be completed in July 2011

Minor traffic movements and noise from construction equipment is ongoing

 

Cumberland Street Carpark

Street works on Cumberland Street to be completed in July 2011

Minor traffic movement and construction noise is ongoing

 

   